What is an interagency review team (IRT) in mitigation banking?

If you've sat through a pre-application meeting for a new mitigation bank, you've heard the term thrown around like everyone already knows what it means. An Interagency Review Team, or IRT, is the group of federal and state agency staff who evaluate your bank instrument and decide whether the site, the credits, and the long-term management plan hold up. The Corps of Engineers chairs it. Everyone else at the table has a say but no single vote.
Who sits on the IRT
The Corps district office runs the review and signs the final instrument, but the room is bigger than that. EPA shows up on most reviews. Fish and Wildlife Service and NOAA Fisheries weigh in when listed species or their habitat are anywhere near the site. State wildlife agencies and state environmental agencies usually have a seat too, especially if the bank is also seeking state in-lieu-fee or state wetland permitting credit. NRCS sometimes joins if the parcel has agricultural drainage history that affects hydrology.
None of these agencies can force the Corps to approve or deny a bank. What they can do is flag a problem loudly enough that the Corps won't sign off until it's fixed. A Fish and Wildlife comment about a species survey gap, or an EPA concern about the credit release schedule, will sit in the file and stall the instrument until you respond to it in writing.
How the IRT moves a bank from prospectus to approval
The process has a few fixed stages, and knowing where you are in them tells you what the IRT wants from you at that moment.
Prospectus. You submit a short document describing the proposed site, the service area, the resource type, and a rough credit estimate. This is where the IRT forms its first impression. A prospectus built on a hunch about connectivity or patch condition, without anything to back it up, is the single biggest reason reviews drag into a second or third round of comments. Agencies ask the same questions a field ecologist would ask: how fragmented is the surrounding landscape, what's the edge-to-interior ratio on the proposed habitat blocks, does this site actually link to anything worth linking to.
Draft instrument. Once the IRT doesn't object to the prospectus, you move to drafting the full mitigation banking instrument: credit release schedule, performance standards, long-term management and financial assurances. The IRT reviews this collectively, usually with a 30-day comment window, though a complicated site can mean rounds of comments going back and forth for months.
Site visit. Most IRTs want to walk the ground, particularly if the bank is proposing stream or wetland credits tied to a specific restoration design. This is also where disagreements between agencies tend to surface, since a Fish and Wildlife biologist and a Corps regulator don't always read the same stand of trees the same way.
Final instrument and signature. Once comments are resolved, the Corps signs the instrument, usually with concurrence noted from the other IRT members. The bank is now approved and can begin releasing credits as performance standards are met.
Where most banks lose time
The delays rarely come from disagreement about whether mitigation is needed. They come from an IRT asking for baseline data that wasn't gathered up front: condition of adjacent parcels, degree of fragmentation in the surrounding watershed, whether the proposed corridor connects two blocks of habitat or just looks like it does on a hand-drawn site plan. Commissioning a full ecology survey before you even know if a parcel is defensible is expensive, and it's often the wrong order of operations.
A faster route is to screen candidate parcels with a land cover classification and fragmentation metrics, patch size, edge density, connectivity between blocks, before you commit to a survey contract. Habitat Suitability builds that screening layer from annual high-res satellite data for whatever study area you define, so you walk into the prospectus stage with numbers instead of a guess.
If you're sorting through candidate sites before you've picked which one is worth a bespoke survey, that's exactly the gap Habitat Suitability is built to close.